NUSANTARAIndonesia's Nusantara Capital Authority (OIKN) has reported average physical construction progress of 32.83 percent across the new capital's judiciary precinct and 25.40 percent in the legislative district. The figures followed an inspection tour by OIKN Head Basuki Hadimuljono in Nusantara's Central Government Core Area (KIPP) in East Kalimantan, moving from the Plenary Assembly Hall site to the Supreme Court complex.
Within the legislative cluster, built under integrated design-and-build contracts, construction of the People's Consultative Assembly (MPR) building led at 24.33 percent completion, followed by the Regional Representative Council (DPD) at 22.75 percent. Physical progress on the House of Representatives (DPR) I building stood at 21.91 percent, DPR II at 21.66 percent, and the Plenary Assembly Hall at 20.25 percent.

Road Connectivity and Judiciary Cluster
Road infrastructure in the legislative district progressed considerably faster than vertical building structures, reaching 41.49 percent completion. Authorities prioritize early road networks to link core government zones across KIPP, smooth heavy construction logistics, and prepare utility corridors ahead of ministerial operations.
Across the judiciary complex, the Supreme Court building and Justice Plaza reached 26.52 percent completion, while the Constitutional Court and Judicial Commission complex reached 25.27 percent alongside 46.69 percent road completion. Deputy for Facilities and Infrastructure Aswin Grandiarto Sukahar said office construction stays within scheduled targets, though contractors must maintain pace and accelerate work to meet year-end deliverables.
Private Investment and Sponge City Drainage
Beyond state facilities, Basuki reviewed a Rp1.25 trillion mixed-use development by Chinese investor PT Star Bright International Investment in the KIPP 1B zone, where construction began in July 2026. He stressed strict adherence to design standards and execution discipline so private developments match commercial market expectations.
Officials also inspected the SM-02 retention pond, a 243,000-cubic-meter basin now roughly 70 percent complete under Nusantara's sponge city runoff strategy. Overall retention basin packages stood at 33.91 percent as of November 10, with OIKN projecting 56.62 percent completion by year-end to strengthen flood resilience and water conservation while completing the executive, legislative, and judicial branches of the new capital.